Sauk River, Rockport, WA

Sauk River, Rockport, WA

Washington State Department of Transportation. Work required driving steel H piles along the river’s edge along the highway to secure the placement of logs with root wads to prevent the river from washing the road away. The project included 2,200 CY roadway excavation including haul; 5,600 CY common borrow including haul; 2,461 ton gravel borrow including haul; 5,832 ton heavy loose rip rap; 5,390 ton quarry spalls; 6,944 LF furnish steel piling; 112 ea drive steel pile; 7,000 SY plane bit pavement; 718 ton commercial HMA; 4,160 SY temp erosion control blanket; 670 LF turbidity curtain.